SIDEWALK CLOSURE - East Side of Vine Street B/W Selma & Sunset, 2/16 - 5/29

Camden's Walk of Fame Restoration Project

PLEASE NOTE THAT THIS EASTERN SIDEWALK OF VINE WILL BE CLOSED during this construction. ETA for reopening is summer 2015. The south side of the sidewalk (by Chase Bank) will be repaired first, followed by the repair of the north side of the sidewalk, adjacent to the Camden development.

SULLY MILLER ONSITE FOREMAN

Chris Olsen: 714.493.3558.

TOTUM CORP CONSTRUCTION MANAGER

Daniel Caruthers: 310.351.4280

LAS ENGINEER OF RECORDS

Linda Siegel: 949.364.1641

Description of Work

  1. Mobilize and set up traffic control per approved LADOT traffic control plan.
  2. Setup temporary site construction fencing and concrete K-rail.
  3. Saw cut existing terrazzo sidewalk paving.
  4. Remove and store existing 43 stars to be installed at a later date.
  5. Relocate existing Zip Car station.
  6. Relocate existing Metro bus stations and existing parking meters.
  7. Demo and remove the existing terrazzo sidewalk and sub-slab.
  8. Excavate and re-compact the sub-grade, pour back a new sub-slab, demo sections of existing curb and gutter and replace with new.
  9. Remove existing Chase Bank drive approach on Vine Street and pour back in a two
  10. part section.
  11. Will maintain an exit drive isle at all times for bank customers.
  12. Pour back the terrazzo sidewalk along with re-installing the stars that were previously removed.
  13. Tree well's will be installed with DG and brick pavers at perimeter of tree well's per contract documents.
  14. Turn back over to the public only after successfully passing the city's slip test inspection.

 

WHEN
February 16, 2015 at 12am - August 15, 2015
WHERE
CHASE Bank Branch and ATM
1500 N Vine St Hollywood
Los Angeles, CA 90038
United States
Google map and directions
CONTACT
Chris Olsen · 7144933558

get updates